Statkraft to build its first wind farms in the world’s southernmost country Chile

(Santiago/Oslo, 12 April, 2021) Statkraft, Europe’s largest renewable energy generator, will build its first wind farms in Chile, expanding its renewable energy generation capacity in the South American country amid an increasing demand for hydro, wind and solar power in the southernmost nation in the world.

Combined with the company’s existing hydropower assets, Statkraft will reach a generating capacity of 366 megawatt (MW) by the end of 2023. The 102 MW Torsa wind power project consists of three wind farms, totalling 19 wind turbines supplied by German manufacturer Nordex.

In total, the wind farms are expected to produce more than 300 GWh of renewable energy annually; enough power to supply 100,000 average Chilean households. The project is located in the O’Higgins region, 124 kilometres south of the capital Santiago.

“These three wind farms are not only expanding our generating capacity in Chile; it is broadening our renewable energy portfolio by including wind power for the first time. Going forward, we’re also planning to include solar power into our generation mix,” says Executive Vice President, International Power in Statkraft, Jürgen Tzschoppe.

“The South American nation is an attractive market for Statkraft and we want to capitalize on our combined expertise in power generation and market operations to best serve the market and provide energy to large industrial customers in the country,” he adds.

Construction will start during the second semester of 2021, and the first wind turbines are expected to start operation in October 2022. The project will utilise the Nordex N163/5.X wind turbine, the same type of turbines utilised in Statkraft’s ongoing Ventos de Santa Eugenia project (519MW) in Brazil. With a diameter of 163 meters, the rotors will cover an area equal to almost three standard football pitches.

Statkraft has been present in Chile since 2014 and the company now owns a production capacity of 209 MW with an annual production of 747 GWh (2020).

Facts about Torsa wind project

Number of turbines: 19
Installed capacity: 102 MW
Turbine manufacturer: Nordex
Turbine type: N163/5.X
Annual generation: More than 300 GWh (enough to supply 100,000 Chilean households)
Location: Northern part of O’Higgins region, 124 km south of Santiago
Construction start: Second half of 2021
Expected completion: December 2022

Three wind farms:

Cardonal – finalised October 2022
Manantiales – finalised November 2022
Los Cerillos – finalised December 2022

About Statkraft
Statkraft is a leading company in hydropower internationally and Europe’s largest generator of renewable energy. The Group produces hydropower, wind power, solar power, gas-fired power and supplies district heating. Statkraft is a global company in energy market operations. Statkraft has 4,500 employees in 17 countries.

 

Attachment

  • Infographic Torsa wind project

Disclaimer & Cookie Notice

Welcome to GOLDEA services for Professionals

Before you continue, please confirm the following:

Professional advisers only

I am a professional adviser and would like to visit the GOLDEA CAPITAL for Professionals website.

Important Notice for Investors:

The services and products offered by Goldalea Capital Ltd. are intended exclusively for professional market participants as defined by applicable laws and regulations. This typically includes institutional investors, qualified investors, and high-net-worth individuals who have sufficient knowledge, experience, resources, and independence to assess the risks of trading on their own.

No Investment Advice:

The information, analyses, and market data provided are for general information purposes only and do not constitute individual investment advice. They should not be construed as a basis for investment decisions and do not take into account the specific investment objectives, financial situation, or individual needs of any recipient.

High Risks:

Trading in financial instruments is associated with significant risks and may result in the complete loss of the invested capital. Goldalea Capital Ltd. accepts no liability for losses incurred as a result of the use of the information provided or the execution of transactions.

Sole Responsibility:

The decision to invest or not to invest is solely the responsibility of the investor. Investors should obtain comprehensive information about the risks involved before making any investment decision and, if necessary, seek independent advice.

No Guarantees:

Goldalea Capital Ltd. makes no warranties or representations as to the accuracy, completeness, or timeliness of the information provided. Markets are subject to constant change, and past performance is not a reliable indicator of future results.

Regional Restrictions:

The services offered by Goldalea Capital Ltd. may not be available to all persons or in all countries. It is the responsibility of the investor to ensure that they are authorized to use the services offered.

Please note: This disclaimer is for general information purposes only and does not replace individual legal or tax advice.