EDMONTON, Alberta, Sept. 01, 2021 (GLOBE NEWSWIRE) — Mineworx Technologies Ltd., (the “Company” or “Mineworx“) (TSXV: MWX) (OTCQB: MWXRF) (FSE: YRS WKN: A2DSW3) is pleased to announce that the 100L pilot plant has successfully completed Stages 1 and 2 of the testing plan.

Stage 1 – Integrity Testing; the goal of this stage was to have all equipment operating with water to confirm that all the systems functioned as expected and that there were no leaks.

Stage 2 – Process Testing; the goal of this stage was to ensure material flowed through the system as designed and that there were no bottlenecks or blockages.

In addition to the primary goals of the first two stages there are other system checks and protocols that were required to be conducted. This includes:

  • Determining that all the sub-systems met the design parameters and functioned within the required tolerances.
  • Checking control systems, both automated and manual, to ensure that the pilot plant can be operated in a safe manner.
  • Implementing appropriate safety and operational procedures for the successful start-up and operation of the pilot plant.

The team is now commencing Stage 3 – Baseline testing; This is designed to replicate the laboratory results with the full chemistry and utilizing feedstock containing platinum and palladium provided by our partner, Davis Recycling Inc.

Upon successful completion of the Stage 3 testing, the pilot plant will be relocated to a facility in Tennessee, that is currently being prepared by the Davis team, for Process Optimization testing. This relocation is expected to occur by the end of September 2021.

These testing stages will provide Mineworx with all the required learnings to allow the Company to move forward with the commercial scale processing plant.

About Mineworx

Mineworx is positioned for growth in the catalytic converter and mining sectors through the development and commercialization of its proprietary, environmentally friendly processing technologies for the recovery of precious metals. Initial focus is the extraction of platinum and palladium from diesel catalytic converters with its partner Davis Recycling and will be building its first commercial extraction facility in Tennessee, USA. The company is also furthering the development of a historic iron ore concession which it holds a 100% interest in South-Eastern Spain. For further information go to www.mineworx.net  

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

For further information contact:

MINEWORX TECHNOLOGIES LTD.

Dave Burwell
Vice President
The Howard Group
(403) 410-7907
dave@howardgroupinc.com

Disclaimer & Cookie Notice

Welcome to GOLDEA services for Professionals

Before you continue, please confirm the following:

Professional advisers only

I am a professional adviser and would like to visit the GOLDEA CAPITAL for Professionals website.

Important Notice for Investors:

The services and products offered by Goldalea Capital Ltd. are intended exclusively for professional market participants as defined by applicable laws and regulations. This typically includes institutional investors, qualified investors, and high-net-worth individuals who have sufficient knowledge, experience, resources, and independence to assess the risks of trading on their own.

No Investment Advice:

The information, analyses, and market data provided are for general information purposes only and do not constitute individual investment advice. They should not be construed as a basis for investment decisions and do not take into account the specific investment objectives, financial situation, or individual needs of any recipient.

High Risks:

Trading in financial instruments is associated with significant risks and may result in the complete loss of the invested capital. Goldalea Capital Ltd. accepts no liability for losses incurred as a result of the use of the information provided or the execution of transactions.

Sole Responsibility:

The decision to invest or not to invest is solely the responsibility of the investor. Investors should obtain comprehensive information about the risks involved before making any investment decision and, if necessary, seek independent advice.

No Guarantees:

Goldalea Capital Ltd. makes no warranties or representations as to the accuracy, completeness, or timeliness of the information provided. Markets are subject to constant change, and past performance is not a reliable indicator of future results.

Regional Restrictions:

The services offered by Goldalea Capital Ltd. may not be available to all persons or in all countries. It is the responsibility of the investor to ensure that they are authorized to use the services offered.

Please note: This disclaimer is for general information purposes only and does not replace individual legal or tax advice.