Skip to main content

Maxim Power Corp. Provides M2 Operations Update, CCGT Project Update and Updated Investor Presentation

CALGARY, Alberta, Dec. 23, 2021 (GLOBE NEWSWIRE) — Maxim Power Corp. (“MAXIM” or the “Corporation”) (TSX: MXG) provides an update on its 204 MW Milner 2 (“M2”) operations, the combined cycle gas turbine (“CCGT”) expansion of M2 project, and updated Investor Presentation.

M2 OPERATIONS UPDATE

As previously reported, M2 initiated a routine planned maintenance outage on November 9, 2021 and also performed work to integrate several critical components of the CCGT expansion of M2. The outage was completed on November 30, 2021 and M2 returned to normal operation on December 1, 2021.

M2 CCGT PROJECT UPDATE

As a result of work performed during the planned maintenance outage in November, M2 has successfully increased its maximum electrical interconnection capacity with the Alberta Electric System Operator to 300 MW to facilitate the CCGT expansion of M2, which is not anticipated to be in commercial operation until December 2022. In the meantime, MAXIM is authorized to operate the legacy 144 MW H.R. Milner facility (“M1”) in tandem with the M2 facility, up to a combined total output of 300 MW. MAXIM has successfully demonstrated two-unit operation from both M1 and M2 with each unit operating as stand-alone power plants. This significant milestone confirms the interconnection is complete to allow for the CCGT expansion of M2. MAXIM notes that M1 as a stand-alone power plant is subject to federal greenhouse gas regulations which limit the annual hours of operation from the unit. MAXIM does not anticipate fully utilizing the M1 unit up to its authorized maximum operating hours.

Progress continues on the engineering and construction of the CCGT expansion of M2 and as of this date the project remains on schedule with no change to the previously reported estimated project costs of $135 million.

At this time, MAXIM forecasts it has sufficient liquidity to complete the CCGT expansion of M2 and will fund the project using cash on hand, operating cashflows and available funds through the existing senior and subordinated credit facilities, as required.

UPDATED INVESTOR PRESENTATION

An updated investor presentation has been prepared for readers and can be accessed through MAXIM’s website in the Investors section.

About MAXIM

Based in Calgary, Alberta, MAXIM is one of Canada’s largest truly independent power producers. MAXIM is now focused entirely on power projects in Alberta. Its core asset – the 204 MW H.R. Milner Plant, M2, in Grande Cache, AB – is a state-of-the-art natural gas-fired power plant that commissioned in Q2, 2020. MAXIM is currently increasing the capacity of M2 to approximately 300 MW and concurrently will realize an improvement in the efficiency of the plant by investing in heat recovery combined cycle technology. In addition, MAXIM continues to explore additional development options in Alberta including its currently permitted gas-fired generation project and the permitting of its wind power generation project. MAXIM trades on the TSX under the symbol “MXG”. For more information about MAXIM, visit our website at www.maximpowercorp.com. For further information please contact:

Bob Emmott, President and COO, (403) 263-3021

Kyle Mitton, CFO and Vice President, Corporate Development, (403) 263-3021

This press release contains forward-looking statements and forward-looking information (collectively “forward looking information”) within the meaning of applicable securities laws relating to MAXIM’s plans and other aspects of MAXIM’s anticipated future operations, management focus, objectives, strategies, financial, operating and production results. Forward-looking information typically uses words such as “anticipate”, “believe”, “project”, “expect”, “goal”, “plan”, “intend”, “may”, “would”, “could” or “will” or similar words suggesting future outcomes, events or performance. The forward-looking statements contained in this press release speak only as of the date thereof and are expressly qualified by this cautionary statement. Specifically, this press release contains forward-looking information concerning, among other things, the expected run time of M1, the expected completion date of the CCGT expansion of M2, the current cost estimates for the CCGT expansion of M2 and MAXIM’s financing plans with respect to the CCGT expansion.

Management has included the forward-looking statements above and a summary of assumptions and risks related to forward-looking statements provided in this press release in order to provide readers with a more complete perspective on MAXIM’s future plans and operations and such information may not be appropriate for other purposes.

MAXIM’s actual results, performance or achievement could differ materially from those expressed in, or implied by, these forward-looking statements and, accordingly, no assurance can be given that any of the events anticipated by the forward-looking statements will transpire or occur, or if any of them do so, what benefits that MAXIM will derive there from. Readers are cautioned that the foregoing lists of factors are not exhaustive. These forward-looking statements are made as of the date of this press release and MAXIM disclaims any intent or obligation to update publicly any forward-looking statements, whether as a result of new information, future events or results or otherwise, other than as required by applicable securities laws. 

Disclaimer & Cookie Notice

Welcome to GOLDEA services for Professionals

Before you continue, please confirm the following:

Professional advisers only

I am a professional adviser and would like to visit the GOLDEA CAPITAL for Professionals website.

Important Notice for Investors:

The services and products offered by Goldalea Capital Ltd. are intended exclusively for professional market participants as defined by applicable laws and regulations. This typically includes institutional investors, qualified investors, and high-net-worth individuals who have sufficient knowledge, experience, resources, and independence to assess the risks of trading on their own.

No Investment Advice:

The information, analyses, and market data provided are for general information purposes only and do not constitute individual investment advice. They should not be construed as a basis for investment decisions and do not take into account the specific investment objectives, financial situation, or individual needs of any recipient.

High Risks:

Trading in financial instruments is associated with significant risks and may result in the complete loss of the invested capital. Goldalea Capital Ltd. accepts no liability for losses incurred as a result of the use of the information provided or the execution of transactions.

Sole Responsibility:

The decision to invest or not to invest is solely the responsibility of the investor. Investors should obtain comprehensive information about the risks involved before making any investment decision and, if necessary, seek independent advice.

No Guarantees:

Goldalea Capital Ltd. makes no warranties or representations as to the accuracy, completeness, or timeliness of the information provided. Markets are subject to constant change, and past performance is not a reliable indicator of future results.

Regional Restrictions:

The services offered by Goldalea Capital Ltd. may not be available to all persons or in all countries. It is the responsibility of the investor to ensure that they are authorized to use the services offered.

Please note: This disclaimer is for general information purposes only and does not replace individual legal or tax advice.