Heidelberg Cement and FLSmidth collaborate on the world’s first carbon capture installation in cement

The well-known carbon capture and storage (CCS) project at Norcem Brevik in Norway – the first of its kind is taking shape. In February 2021, Heidelberg and FLSmidth signed an agreement for FLSmidth to deliver the necessary plant modifications allowing for downstream CO2 removal. Final commissioning is scheduled for the first half of 2024.  

Carbon capture is considered to be one of the key technologies in solving the CO2 emission challenges in hard-to-abate sectors, like cement. Emitting approximately 7% of the world’s carbon emissions, the cement industry is attacking the challenge from all possible angles. Heidelberg Cement’s Norcem Brevik plant is now prepared to become the first cement producer in the world to move from test into full-scale production after years of preparation together with FLSmidth and other technology providers.

The capturing process at the Norcem Brevik plant will use a mixture of water and organic solvents to remove the CO2. But before CO2 can be removed, the production process must be adjusted, and particles in the flue gas removed. FLSmidth have the plant knowledge and the necessary expertise in air pollution control for this rebuild of the plant.

“We are very excited to have FLSmidth on board and to finally begin the construction of the full-size installation,” says Tor Gautestad, Project Manager at Norcem. “FLSmidth’s extensive process knowledge, and air pollution control in particular, will be critical to the success of the project,” Mr Gautestad adds.

“Having installed more than 4,000 filters around the world, I can say that “Brevik CCS” is no ordinary project. We are looking forward to working with Norcem on unleashing the potential of the project,” says Carsten Riisberg Lund, Cement Industry President, FLSmidth.

The agreement between Heidelberg and FLSmidth is effective and work on site will start during the winter shutdown in 2022 and is scheduled to end early 2024.  

Contacts

Media Relations
Rasmus Windfeld, +45 40 44 60 60, rwin@flsmidth.com

Investor Relations

Nicolai Mauritzen, +45 30 93 18 51, nicm@flsmidth.com

FLSmidth provides sustainable productivity to the global mining and cement industries. We deliver market-leading engineering, equipment and service solutions that enable our customers to improve performance, drive down costs and reduce environmental impact. Our operations span the globe and we are close to 10,700 employees, present in more than 60 countries. In 2020, FLSmidth generated revenue of DKK 16.4 billion. MissionZero is our sustainability ambition towards zero emissions in mining and cement by 2030.

www.flsmidth.com/MissionZero

Attachment

  • Heidelberg_FLSmidth order

Disclaimer & Cookie Notice

Welcome to GOLDEA services for Professionals

Before you continue, please confirm the following:

Professional advisers only

I am a professional adviser and would like to visit the GOLDEA CAPITAL for Professionals website.

Important Notice for Investors:

The services and products offered by Goldalea Capital Ltd. are intended exclusively for professional market participants as defined by applicable laws and regulations. This typically includes institutional investors, qualified investors, and high-net-worth individuals who have sufficient knowledge, experience, resources, and independence to assess the risks of trading on their own.

No Investment Advice:

The information, analyses, and market data provided are for general information purposes only and do not constitute individual investment advice. They should not be construed as a basis for investment decisions and do not take into account the specific investment objectives, financial situation, or individual needs of any recipient.

High Risks:

Trading in financial instruments is associated with significant risks and may result in the complete loss of the invested capital. Goldalea Capital Ltd. accepts no liability for losses incurred as a result of the use of the information provided or the execution of transactions.

Sole Responsibility:

The decision to invest or not to invest is solely the responsibility of the investor. Investors should obtain comprehensive information about the risks involved before making any investment decision and, if necessary, seek independent advice.

No Guarantees:

Goldalea Capital Ltd. makes no warranties or representations as to the accuracy, completeness, or timeliness of the information provided. Markets are subject to constant change, and past performance is not a reliable indicator of future results.

Regional Restrictions:

The services offered by Goldalea Capital Ltd. may not be available to all persons or in all countries. It is the responsibility of the investor to ensure that they are authorized to use the services offered.

Please note: This disclaimer is for general information purposes only and does not replace individual legal or tax advice.