BW Offshore: Second quarter and first half results 2026

Second quarter and first half results 2026

HIGHLIGHTS

  • BW Opal in stable production with Practical Completion moved to Q2 2027
  • EBITDA USD 62.5 million in Q2 and USD 110.4 million for the first half-year
  • Non-cash impairment charge of USD 125 million on BW Opal; net loss of USD 102.1 million in Q2 and loss of USD 78.7 million for the first half-year
  • Underlying net profit of USD 46.6 million for the first half-year, excluding the non-cash impairment
  • Operating cash flow USD 41.5 million in Q2 and USD 84.8 million for the first half-year
  • Extended BW Catcher contract to end-2030, adding approximately USD 490 million to firm backlog
  • Signed FEED with Equinor for Bay du Nord FPSO and opened local office in St. John’s
  • Equity ratio 28.3% and USD 511 million in available liquidity
  • Q2 cash dividend USD 0.063 per share equivalent to USD 11 million
  • Full-year 2026 EBITDA guidance revised to USD 250-280 million with limited cash flow impact
  • Strategic review ongoing – timeline impacted by extended Practical Completion for BW Opal

BW Opal is currently producing at 85% of nameplate capacity, delivering revenues in line with production. On 15 June, BW Opal achieved the Interim Performance Test (IPT), confirming that key production, processing and utility systems operate in an integrated manner and deliver stable performance under production conditions. As production increased, certain technical issues tied to third-party delivered equipment have been identified and need to be resolved before Practical Completion. Due to long lead times for membranes and to keep production impact to a minimum in close coordination with the client, replacements are expected to be executed in the first quarter of 2027.

As a result, BW Offshore expects to incur approximately USD 65 million of incremental investment until Practical Completion, largely offset by additional revenue generated before commencement of the firm contract.

A non-cash impairment charge of USD 125 million was recognised on BW Opal, after moving Practical Completion to the second quarter of 2027. The impairment has no impact on liquidity and contract backlog. The 15-year fixed-term contract will commence on Practical Completion. The impairment charge is triggered due to additional cost to complete as well as additional borrowing cost to be capitalised until completion of BW Opal. The extended timeline to realise Practical Completion was identified, analysed and concluded by management in August 2026.

“BW Offshore has full focus on maintaining stable production from BW Opal in close collaboration with the client,” said Marco Beenen, CEO of BW Offshore. “Elsewhere, we have high activity on the Bay du Nord project, executing the extensive FEED in preparation for contract award by Equinor early next year.”

With Practical Completion for BW Opal being moved into 2027, full-year EBITDA guidance has been revised to a range of USD 250 to 280 million, from the previous range of USD 310 to 340 million. The underlying cash flow impact in 2026 is limited as BW Opal continues to generate revenue under the interim volume-based contract, while the majority of the additional investment falls into 2027. Of the revision, approximately USD 40 million relates to amortisation of prepayments with no cash effect, limiting the net cash impact in 2026 to approximately USD 10 million.

The Board of Directors has declared a quarterly cash dividend of USD 0.063 per share. The shares will trade ex-dividend from 27 August 2026. Shareholders recorded in VPS following the close of trading on Oslo Børs on 28 August 2026, will be entitled to the distribution payable on or around 7 September 2026. The Company reiterates its commitment to maintaining an attractive shareholder return programme.

In early June, BW Offshore opened a local office in St. John’s, Newfoundland and Labrador, to strengthen its local presence during the Front-End Engineering and Design (FEED) phase and in preparation for the operating phase for the Bay du Nord FPSO project.

BW Offshore announced a strategic review on 5 December 2025. The strategic review is ongoing with interested parties conducting due diligence, but timeline is impacted by the revised Practical Completion of BW Opal. The Company’s main strategic focus of growing the FPSO business supported by an optimised capital structure and strong partnerships remains unchanged.

On 30 June 2026, the firm and probable backlog measured by expected cash flow from operations amounted to USD 2.2 billion of which 97% is firm backlog.

Please see attached the Q2 Presentation. The earnings tables are available at:

https://bwoffshore.com/financials

BW Offshore will host a webcast of the financial results 09:00 (CEST) today. The presentation will be given by CEO Marco Beenen and CFO Ståle Andreassen.

Webcast information:
You can follow the presentation via webcast with supporting slides and a Q&A module, available on:

BW Offshore Limited – Q2 presentation webcast

Please note, that if you follow the webcast via the above URL, you will experience a 30 second delay compared to the main conference call. The web page works best in an updated browser – Chrome is recommended.

For further information, please contact:
Ståle Andreassen, CFO, +47 91 71 86 55
IR@bwoffshore.com or www.bwoffshore.com

About BW Offshore:
BW Offshore engineers innovative floating production solutions. The Company has a fleet of FPSOs and floating wind solutions. By leveraging four decades of offshore operations and project execution, the Company creates tailored offshore energy solutions for evolving markets worldwide. BW Offshore has around 900 employees and is publicly listed on the Oslo stock exchange.

This information is subject to the disclosure requirements pursuant to Section 5-12 the Norwegian Securities Trading Act

Attachments

Disclaimer & Cookie Notice

Welcome to GOLDEA services for Professionals

Before you continue, please confirm the following:

Professional advisers only

I am a professional adviser and would like to visit the GOLDEA CAPITAL for Professionals website.

Important Notice for Investors:

The services and products offered by Goldalea Capital Ltd. are intended exclusively for professional market participants as defined by applicable laws and regulations. This typically includes institutional investors, qualified investors, and high-net-worth individuals who have sufficient knowledge, experience, resources, and independence to assess the risks of trading on their own.

No Investment Advice:

The information, analyses, and market data provided are for general information purposes only and do not constitute individual investment advice. They should not be construed as a basis for investment decisions and do not take into account the specific investment objectives, financial situation, or individual needs of any recipient.

High Risks:

Trading in financial instruments is associated with significant risks and may result in the complete loss of the invested capital. Goldalea Capital Ltd. accepts no liability for losses incurred as a result of the use of the information provided or the execution of transactions.

Sole Responsibility:

The decision to invest or not to invest is solely the responsibility of the investor. Investors should obtain comprehensive information about the risks involved before making any investment decision and, if necessary, seek independent advice.

No Guarantees:

Goldalea Capital Ltd. makes no warranties or representations as to the accuracy, completeness, or timeliness of the information provided. Markets are subject to constant change, and past performance is not a reliable indicator of future results.

Regional Restrictions:

The services offered by Goldalea Capital Ltd. may not be available to all persons or in all countries. It is the responsibility of the investor to ensure that they are authorized to use the services offered.

Please note: This disclaimer is for general information purposes only and does not replace individual legal or tax advice.