Endeavour Reports Positive PFS Results For Both Fetekro and Kalana, Confirming Strong Organic Growth Pipeline
1Post-tax, based on a gold price of $1,500/ozThe PFS summary metrics and project economics for the Fetekro and Kalana projects are shown in Tables 2 and 3 below.Table 2: PFS Summary 1Based ona gold price of $1,500/oz. 2 GHG Emissions Intensity calculated as Scope 1 and 2 emissions.Table 3: Project Economics1 Payback period calculated starting from start of commercial productionFETEKRO PROJECT PRE-FEASIBILITY STUDYEndeavour expects to file a Technical Report pursuant to National Instrument 43-101 – Standards of Disclosure for Mineral Projects (“the NI 43-101”) in respect of the Fetekro PFS within a 45-day period.OverviewEndeavour began exploration on the Fetekro greenfield project in March 2017, following a strategic assessment of its exploration tenements which identified the project as a top priority target.A maiden Mineral Resource was published on October 29, 2018 and was subsequently updated on September 3, 2019 and August 18, 2020. A positive Preliminary Economic Assessment (“PEA”), based on the 2019 Indicated Resource, was published on August 18, 2020.As a result of the positive PEA results, a PFS was expedited to evaluate the economic potential of the updated 2020 Indicated Resource. Lycopodium Minerals Pty Ltd (“Lycopodium”) was responsible for the compilation of the report and delivery of the PFS to Endeavour. For the mining section, Lycopodium was assisted by Snowden Group (“Snowden”) and for the infrastructure, tailing storage facility (“TSF”) and water management sections assisted by Knight Piesold.As shown in Figure 1 below, the PFS demonstrates Fetekro’s ability to deliver 220kozpa over the first five years and 209kozpa over its 9.5-year mine life, with further significant exploration opportunities.Figure 1: Fetekro 2021 PFS Production Profile
Notes: For details regarding the 2020 PEA Study, please refer to the press release dated August 18, 2020, available on Endeavour’s website.Reserves and ResourcesAs shown in Table 5 below, a total of 2.1Moz were converted into a maiden Probable Reserve out of an Indicated Resource base of 2.5Moz, representing a conversion ratio of 85%.The PFS is based on the updated 2020 Mineral Resource Estimate (“MRE”), as published on August 18, 2020, which outlined a 108% increase over the resource base used for the PEA. The Fetekro Reserves and Resources, which comprises only the Lafigué deposit, are shown in the table below. The Inferred material within the pit design was treated as waste.Table 5: Lafigué Mineral Reserves and Resource
Mineral Reserve Estimates follow the Canadian Institute of Mining, Metallurgy and Petroleum (“CIM”) Definitions Standards for Mineral Resources and Reserves and have been completed in accordance with the Standards of Disclosure for Mineral Projects as defined by National Instrument 43-101. Reported tonnage and grade figures have been rounded from raw estimates to reflect the relative accuracy of the estimate. Minor variations may occur during the addition of rounded numbers. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. Resources were constrained by MII Pit Shell and based on a cut-off of 0.5 g/t Au and $1,500/oz gold price. The Qualified Person for the Mineral Resources and Reserves is Kevin Harris CPG, VP Resources.Mining OperationsThe Lafigué deposit is near surface and amenable to conventional open-pit mining. The mine planning, resource and cost estimation for the PFS is based on a contract mining operation with a maximum mining movement of 50 million tonnes per (“Mt”) per year with the variation largely due to different productivities by weathering type. The Lafigué pit will be developed in eight stages. Stockpiles are expected to be accumulated to allow high-grade material to be preferentially processed.Processing OperationsOre will be processed via a 3.0 to 3.3 Mtpa processing plant. Ore feed will be above the nominal capacity for the first two years of processing due to the presence of more highly weathered ore. Over the life of mine, the plant will be fed with approximately 92% fresh ore and 8% oxide/transitional ore.Primary jaw crushing will produce a coarse crushed product, which will feed a secondary conventional cone crusher and high-pressure grinding roll. Ore will be milled to 80% passing 75µm (microns), at which point a gravity circuit will remove coarse free-milling gold. Gravity concentrate will be treated by intensive cyanidation and electrowinning to produce gold doré.The remaining ore that is not recovered by gravity will be leached in five leach tanks. The leached gold solution will be processed in seven carbon-in-pulp tanks before gold is recovered from loaded carbon in a AARL elution circuit, electrowinning and gold smelting to produce doré.Extensive metallurgical testwork has indicated that gold is free milling with very high gravity and leach extraction potential, with 95% gold recovery expected over the life of mine.Operating Cost SummaryMining operating cost estimates, prepared by Snowden, are based on a small owner’s team managing mining activities using a contract-mining model. Process operating cost estimates were prepared by Lycopodium and General and Administration (“G&A”) cost estimates were prepared by Lycopodium with input from Endeavour, as summarized in the table below.Table 6: Fetekro Life of Mine Operating Unit CostsOperating costs have been based on a delivered diesel price of $0.90 per litre and are in line with current local pricing. Power will be sourced from a combination of the grid supplying 225kv to site and a 7MW solar power plant, with power costs estimated at $0.09/kWh. The addition of the hybrid power plant decreased the estimated LOM unit power cost from $0.12/kwh to $0.09/kwh.Capital Cost and Infrastructure SummaryThe project capital cost estimate was compiled by Lycopodium with input from Knight Piésold on the TSF, water infrastructure, site access roads and airstrip. Endeavour has provided project specific portions for mine establishment and facilities, owners costs and the high voltage power supply.A 22-month construction period is projected with the initial capital cost summarized in the table below.Table 7: Fetekro Capital Cost Estimate Summary (+20/-10%)
The Fetekro Project benefits from minimal resettlement requirements and good infrastructure, including access to the power grid with a 225kv supply within 28km of the project, which will be supplemented by an on-site 7MW solar power plant with an associated capital cost of approximately $7 million. A diesel backup power supply, with an associated capital cost of approximately $24 million plus contingency, may be contemplated within the DFS trade-offs.Downstream raise construction methods will be utilized for all TSF embankment raises of the perimeter embankments. The TSF will comprise a cross-valley storage facility formed by multi-zoned earth fill embankments, comprising a total footprint area (including the basin area) of approximately 114 ha for the Stage 1 TSF increasing to 200 ha for the final TSF. The TSF is designed to accommodate a total of 32.8 Mt of tailings. The Stage 1 TSF is designed for 18 months storage capacity. Subsequently, the TSF will be constructed in annual raises to suit storage requirements; however, this may be adjusted to biennial raises to suit mine scheduling during the operation.As shown in Figure 2 below, the process plant and TSF will be located on the northwestern side of the open pit.Access to the project is by the regional highway B412 and then a sealed road to Yammoussoukro and Bouaké. A 15km stretch of unsealed access road will be upgraded as part of the project and an airstrip will be built 3.5km north of the accommodation village.Figure 2: Schematic Fetekro Site Layout
Notes: Details related to the Avnel 2016 Study, published on March 30, 2016, are available on SEDAR under Avnel’s profile. Comparative period economics are unavailable as a gold price of US$1,200/oz was used in the 2016 Study while $1,500/oz was used in the 2021 Study.Reserves and ResourcesAs shown in Table 9, a total of 1.8Moz were converted into Probable Reserves from an Indicated Resource of 2.3Moz by the 2021 Study for the Kalana Project, representing a conversion ratio of 79%.The 2021 Study is based on recently updated Mineral Resource Estimates (“MRE”), rather than the previous estimate as prepared on behalf of Avnel in 2016.The updated MRE includes the Kalana and Kalanako deposits and two TSFs stemming from the historical underground mine which utilized gravity-only recovery methods. The deposit’s geological models were updated using a more conservative approach to incorporate tighter geological controls for the high-grade nugget effect, stacked vein sets and dilution after additional drilling in 2017-18, as further described in the section below entitled Kalana Technical Notes.Table 9: Kalana Project Mineral Resource and Reserve Evolution
Mineral Reserve and Resource estimates follow the Canadian Institute of Mining, Metallurgy and Petroleum (“CIM”) definitions standards for Mineral Resources and Reserves and have been completed in accordance with the Standards of Disclosure for Mineral Projects as defined by National Instrument 43-101. Reported tonnage and grade figures have been rounded from raw estimates to reflect the relative accuracy of the estimate. Minor variations may occur during the addition of rounded numbers. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. 1The 2020 Updated Kalana Project Mineral Resource has an effective date of June 30, 2020 and is constrained by a $1,500/oz conceptual open-pit shell. For notes relating to the 2020 Resource Estimate, please consult the section below entitled Kalana Technical Notes. 2As per Avnel Mineral Resources as of March 30, 2016, based on $1,400/oz Au; for the notes relating to the 2016 estimate, please consult the Kalana Technical Report dated March 30, 2016 available on the Endeavour website.The Kalana Project comprises two primary deposits, Kalana and Kalanako, and two TSFs, with resources outlined in the table below.Table 10: Updated Kalana Project Mineral Resource Estimate
Mineral Resource estimates follow the Canadian Institute of Mining, Metallurgy and Petroleum (“CIM”) definition standards for Mineral Resources and Reserves and have been completed in accordance with the Standards of Disclosure for Mineral Projects as defined by National Instrument 43-101. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. The Kalana and Kalanako Mineral Resources are constrained by MII $1,500/oz Pit Shell and based on a cut-off of 0.5 Au g/t. The TSF Mineral Resource does not have a cut-off grade applied. Reported tonnage and grade figures have been rounded from raw estimates to reflect the relative accuracy of the estimate. Minor variations may occur during the addition of rounded numbers. The Qualified Person for the exploration data and geological interpretation is Helen Oliver MSc FGS CGeol, Endeavour Mining Group Resource Geologist. The Qualified Person for the Tailings Mineral Resource Estimate is Ms. Oliver. The Qualified Person for the Kalana and Kalanako Mineral Resource Estimate is Paul Blackney BSc Hons MAusIMM MAIG, Optiro Pty. Ltd. The cut-off date for the Kalana drill hole database is 1 July 2018 and 7 February 2018 for the Kalanako drill hole database. The effective date of the MRE is 30 June 2020.The Probable Mineral Reserves for the Kalana Project, inclusive of dilution and mining loss, derived from an Indicated Resource is summarized in the table below.Table 11: Updated Kalana Probable Mineral ReservesNo Proven reserves have been estimated. Mineral Reserve estimates follow the Canadian Institute of Mining, Metallurgy and Petroleum (“CIM”) definitions standards for Mineral Resources have been completed in accordance with the Standards of Disclosure for Mineral Projects as defined by National Instrument 43-101. Reported tonnage and grade figures have been rounded from raw estimates to reflect the relative accuracy of the estimate. Minor variations may occur during the addition of rounded numbers. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.Mining OperationsThe mine planning, resource and cost estimation for the 2021 Study is based on a contract-mining operation with a maximum mining movement of 30Mt per year with the variation largely due to different productivities by weathering type. A high proportion of the orebodies are within the saprolite weathering horizon resulting in approximately 30 to 40% of the material moved requiring no or limited blasting. Nearly 97% of the ore tonnes are from Kalana, the remainder is from Kalanako which is higher grade at a higher strip ratio. The Kalana pit will be developed in six stages while Kalanako will be mined in two stages forming two separate pits.Endeavour elected to use a more conservative approach incorporating fully diluted blocks susceptible for large volume open pit mining rather than small scale selective mining as envisaged in the previous 2017 study.Stockpiles are expected to be accumulated to allow high grade material to be preferentially processed.Processing OperationsThe plant design has been based on a nominal capacity of 3.0Mtpa of primary mineralized material, if fed with fresh rock, and a capacity of 3.8Mtpa if fed with oxide material. Over the life of mine, the plant will be fed with approximately 27% oxide, 9% transition, 62% fresh and 2% tailings material, with the majority of the oxide and tailings processed in the first four years of operation.The 2021 Study envisages a conventional single stage primary crusher, followed by a SABC circuit (SAG and ball mill, with pebble crusher) grinding to 80% passing 90 μm. The grind material will be passed through a gravity concentration circuit to remove coarse gold, which will be subsequently treated by intensive cyanidation and electrowinning to recover gold doré. The remaining feed will be treated by pre-leach thickening and carbon in leach. Loaded carbon will be passed to a split AARL elution circuit, electrowinning and then gold smelting to recover gold from the loaded carbon to produce doré.Metallurgical testwork demonstrates the Kalana ore has high potential for gravity recoverable gold, particularly the oxide ore, and an average total gold recovery of 90% is projected for the life of mine.Operating Cost SummaryMining operating cost estimates, prepared by Snowden, are based on a small owner’s team managing mining activities using a contract-mining model. Process operating cost estimates were prepared by Lycopodium and G&A cost estimates were prepared by Lycopodium with input from Endeavour, as summarized in the table below.Table 12: Kalana Life of Mine Operating Unit Costs
Operating costs have been based on a delivered diesel price of $0.77 per litre and are in line with current local pricing. Power will be derived from the Malian grid with power costs estimated at $0.14/kWh.Capital Cost and Infrastructure SummaryThe project capital cost estimate was compiled by Lycopodium with input from Knight Piésold on the TSF, water infrastructure, site access roads and airstrip. Endeavour have provided the project specific portions of mine establishment and facilities, owners costs and the power supply.A 22-month construction period is expected with the initial capital cost summarized in the Table below.Table 13: Capital Cost Estimate Summary (+20/-10%)
The Kalana Project will be powered by Malian grid power, which will require the construction of a 51km 66 kV power line from Yanfolila and a new sub-station at the project. Additional emergency power will be supplied by onsite 2,000kVA diesel generators.Downstream raise construction methods will be utilized for all TSF embankment raises of the perimeter embankments. The TSF will comprise a two-cell paddock storage facility formed by multi-zoned earth fill embankments, comprising a total footprint area (including the basin area) of approximately 77 ha for the Stage 1 TSF, increasing to 239 ha for the final TSF. The TSF is designed to accommodate a total of 35.6Mt of tailings. The stage one TSF is designed for 18 months storage capacity. Subsequently, the TSF will be constructed in annual raises to suit storage requirements, however this may be adjusted to biennial raises to suit mine scheduling during the operation.As shown in Figure below, the process plant will be located on the north eastern side of the open pit, and the TSF will be located on the south western side of the open pit. The accommodation camp will be located north of the process plant. The airstrip will be located 4km north of the process plant. The 4.9km main access road will approach the site from the south east and connect to the RN8, part of the regional road network between Yanfolila and Bougouni.Figure 5: Kalana Site Layout
Drilling ProceduresThe RC drill programme samples were collected on one metre intervals using dual tube, percussion hammer and a drop centre bit. The material passed through a cyclone which was thoroughly cleaned after every sample by flushing the hole. Samples were split at the drill site using a three-tier riffle splitter with both bulk and laboratory sample weights and moisture recorded. Samples sent to the laboratory are between four and five kilograms in weight. Representative samples for each interval were collected with a spear, sieved into chip trays and retained for reference. Washed chips were also glued onto display boards. A small proportion of the reject sample material was washed for visible gold.Drill core (PQ, HQ and NQ size) samples were selected by Endeavour geologists and sawn in half with a diamond blade at the project site. Half of the core was retained at the site for reference purposes. Sample intervals were generally one metre in length.All samples were transported by road to ALS in Ouagadougou, Burkina Faso or in Kumasi, Ghana, or to the BIGS Global Burkina SARL Laboratory in Ouagadougou in secured, poly-woven bags.Assay ProceduresOn arrival at the analytical laboratory, the RC and DD samples were weighed and crushed to 6 mm (70% passing), and a two-kilogram sample taken by a rotary split which was pulverised to 75 μm (85% passing).The two kilogram pulverised samples were analysed for gold using the LeachWELL (LW) method. LW tails were further analysed by Fire Assay (50 g charge) with an Atomic Absorption (AA) finish when returning an assay of over 0.3 ppm Au.A systematic re-assaying programme of the IAMGOLD-Avnel joint venture drill samples was undertaken in 2013-15 in three (depth constrained) phases due to the visible gold in samples with barren assays. Sample selection criteria was based on:Gold grade above 0.1 g/t, or a sample below 0.1 Au g/t and included in a mineralised intercept.Visible gold.Sample located with a geologically mineralised zone but with no grade.During the re-assay programme, the leaching tails were systematically assayed using fire assay to ensure that the leaching process was complete if the LeachWELL grade was over 0.1 Au g/t. Since 2015, all samples are routinely sent for LeachWELL analysis.Quality Assurance and Quality Control ProceduresThe sampling and assaying in the Kalana Project were monitored through the implementation of a quality assurance/quality control (QA/QC) programme with the use of Certified Reference Materials (“standards”), blanks and duplicates inserted into the sample stream by Endeavour geologists.QA/QC results are reviewed on a certificate basis and “failed” samples are identified and re-assayed according to the Endeavour QA/QC protocol.The Kalana Project exploration database is held within a propriety electronic secure database system with a dedicated Database Manager.QUALIFIED PERSONS
Patrick Pérez, P.Eng , Director of Technical Studies for Endeavour Mining – a registered member of APEGS (Association of Professional Engineers and Geoscientists of Saskatchewan), is a “Qualified Person” as defined by National Instrument 43-101 – Standards of Disclosure for Mineral Projects (“NI 43-101”) and has reviewed and approved the technical information in this news release.CONTACT INFORMATION
The Toronto Stock Exchange has neither reviewed nor accepts responsibility for the adequacy or accuracy of this news release.ABOUT ENDEAVOUR MINING CORPORATIONEndeavour Mining is one of the world’s top ten senior gold producers and the largest in West Africa, with operating assets across Senegal, Cote d’Ivoire and Burkina Faso and a strong portfolio of advanced development projects and exploration assets in the highly prospective Birimian Greenstone Belt across West Africa.A member of the World Gold Council, Endeavour is committed to the principles of responsible mining and delivering sustainable value to its employees, stakeholders and the communities where it operates. Endeavour is listed on the Toronto Stock Exchange, under the symbol EDV and will be seeking a secondary listing as a Premium issuer on the London Stock Exchange during Q2-2021.For more information, please visit www.endeavourmining.com.CAUTIONARY NOTE REGARDING FORWARD-LOOKING INFORMATIONThis press release contains statements which constitute “forward-looking information” within the meaning of applicable securities laws, including statements regarding the plans, intentions, beliefs and current expectations of Endeavour with respect to future business activities and operating performance. Forward-looking information is often identified by the words “may”, “would”, “could”, “should”, “will”, “intend”, “plan”, “anticipate”, “believe”, “estimate”, “expect” or similar expressions and includes information regarding Endeavour’s estimates, expectations, forecasts and guidance for production, all-in sustaining cost, capital expenditures, cost savings, project economics (including net present value and internal rates of return) and other information contained in the feasibility study; as well as references to other possible events, the future price of gold, the estimation of mineral reserves and mineral resources, the realization of mineral reserve and mineral resource estimates, the timing and amount of estimated future production, costs of production, capital expenditures, costs and timing of the development of the project and mining and processing activities, permitting timelines, requirements for additional capital, government regulation of mining operations, and environmental risks.Investors are cautioned that forward-looking information is not based on historical facts but instead reflect Endeavour management’s expectations, estimates or projections concerning future results or events based on the opinions, assumptions and estimates of management considered reasonable at the date the statements are made. Although Endeavour believes that the expectations reflected in such forward-looking information are reasonable, such information involves risks and uncertainties, and undue reliance should not be placed on such information, as unknown or unpredictable factors could have material adverse effects on future results, performance or achievements of the combined company. This forward-looking information may be affected by risks and uncertainties in the combined business of Endeavour and market conditions, including (1) there being no significant disruptions affecting Endeavour’s operations whether due to extreme weather events and other or related natural disasters, labor disruptions, supply disruptions, power disruptions, damage to equipment or otherwise; (2) permitting, development, operations and production for the Fetekro and Kalana projects, respectively, being consistent with Endeavour’s expectations; (3) political and legal developments in Côte d’Ivoire and Mali, respectively, being consistent with current expectations; (4) certain price assumptions for gold; (5) prices for diesel, electricity and other key supplies being approximately consistent with current levels; (6) the accuracy of Endeavour’s mineral reserve and mineral resource estimates; and (7) labor and materials costs increasing on a basis consistent with Endeavour’s current expectations. This information is qualified in its entirety by cautionary statements and risk factor disclosure contained in filings made by Endeavour with the Canadian securities regulators, including Endeavour’s annual information form, financial statements and related MD&A for the financial year ended December 31, 2019 filed with the securities regulatory authorities in certain provinces of Canada and available at www.sedar.com.Should one or more of these risks or uncertainties materialize, or should assumptions underlying the forward looking information prove incorrect, actual results may vary materially from those described herein as intended, planned, anticipated, believed, estimated or expected. Although Endeavour has attempted to identify important risks, uncertainties and factors which could cause actual results to differ materially, there may be others that cause results not to be as anticipated, estimated or intended. Endeavour does not intend, and do not assume any obligation, to update this forward-looking information except as otherwise required by applicable law.Neither the Toronto Stock Exchange nor the Investment Industry Regulatory Organization of Canada accepts responsibility for the adequacy or accuracy of this release.1 As per press release dated June 28, 2017, available on Endeavour’s website.AttachmentsFetekro 2021 PFS Production Profile.jpgSchematic Fetekro Site Layout.jpgFetekro Plan Map with Exploration Targets.jpgKalana Site Layout.jpgKalana Plan Map with Exploration Targets.jpgKalana 2021 PFS Production Profile.jpgView News Release in PDF Format