European Energy A/S: Interim Report H1 2026

European Energy A/S: Interim Report H1 2026

COMPANY ANNOUNCEMENT 13/2026 (28.08.2026)

European Energy announces its financial report for the first half of 2026.

Highlights:

  • EBITDA impacted by delayed project sales: Q2 2026 and H1 2026 revenue of EUR 49m and EUR 129m, respectively. Q2 2026 and H1 2026 EBITDA of EUR 7m and EUR 12m, respectively, primarily reflecting delayed project sales.
  • Outlook 2026 guidance revised: The outlook announced 27 February 2026 with EBITDA expected in the range of EUR 200-300m for 2026 is revised to EUR 175-250m due to the risk of some project sales being postponed into 2027.
  • Stable performance of operational assets: Electricity production of 555 GWh and 1,041 GWh in Q2 2026 and H1 2026, respectively, broadly in line with same periods last year. Gross profit of EUR 29m and EUR 50m in Q2 2026 and H1 2026, respectively, also in line with same periods of last year, however with signals of fundamental improvements going forward.
  • Project sales weighted towards end of H2 2026: Gross profit from project sales of EUR 3m and EUR 7m in Q2 2026 and H1 2026, respectively versus EUR 51m and EUR 99m in same periods last year. A solid and well-progressed pipeline of project sales expected to close primarily at the end of the second half of 2026.
  • Liquidity position comfortable: Senior and hybrid bond issuances of EUR 210m completed during H1 2026 in combination with disciplined cost and investment management provides a comfortable liquidity resources available at end of H1 2026 of EUR 287m.
  • Solid construction activity: 1 GW under construction across 32 sites in 12 countries, including 653 MW solar, 105 MW wind and 295 MW BESS. In H1 2026, nine project achieved commercial operation (COD) with a total capacity of 264 MW measured at effective ownership.
  • BESS rollout progressing: The BESS retrofit program started for operational PV plants in May 2025. In August 2026, seven BESS systems was installed in Denmark and in the Baltics, totalling 167 MW/545 MWh, and additional six projects are under construction in Denmark, the UK, Australia, Poland and the Baltics. The seven installed systems have either started operation or are in final testing and commissioning.
  • Positive momentum in Power-to-X: Growing RFNBO-driven demand for e-methanol resulting in additional offtake agreements signed in the last months as Kassø remains Europe’s only large-scale RFNBO-compliant facility. Also, European Energy was awarded more than EUR 200m in the German hydrogen tender to support the further development of our Power-to-X activities in Denmark.

For further information, please contact Investor Relations: investor.relations@europeanenergy.com

This announcement has been made in accordance with the market abuse regulation (regulation (EU) no. 596/2014 on market abuse).

Attachment

Disclaimer & Cookie Notice

Welcome to GOLDEA services for Professionals

Before you continue, please confirm the following:

Professional advisers only

I am a professional adviser and would like to visit the GOLDEA CAPITAL for Professionals website.

Important Notice for Investors:

The services and products offered by Goldalea Capital Ltd. are intended exclusively for professional market participants as defined by applicable laws and regulations. This typically includes institutional investors, qualified investors, and high-net-worth individuals who have sufficient knowledge, experience, resources, and independence to assess the risks of trading on their own.

No Investment Advice:

The information, analyses, and market data provided are for general information purposes only and do not constitute individual investment advice. They should not be construed as a basis for investment decisions and do not take into account the specific investment objectives, financial situation, or individual needs of any recipient.

High Risks:

Trading in financial instruments is associated with significant risks and may result in the complete loss of the invested capital. Goldalea Capital Ltd. accepts no liability for losses incurred as a result of the use of the information provided or the execution of transactions.

Sole Responsibility:

The decision to invest or not to invest is solely the responsibility of the investor. Investors should obtain comprehensive information about the risks involved before making any investment decision and, if necessary, seek independent advice.

No Guarantees:

Goldalea Capital Ltd. makes no warranties or representations as to the accuracy, completeness, or timeliness of the information provided. Markets are subject to constant change, and past performance is not a reliable indicator of future results.

Regional Restrictions:

The services offered by Goldalea Capital Ltd. may not be available to all persons or in all countries. It is the responsibility of the investor to ensure that they are authorized to use the services offered.

Please note: This disclaimer is for general information purposes only and does not replace individual legal or tax advice.